QuestionWhere do I start a predictive maintenance implementation so that machine condition monitoring produces service decisions rather than just more alarms?
Predictive maintenance, that is maintenance based on a forecast of condition, is meant to deliver repairs planned before a failure, less unplanned downtime and better use of parts. In practice, many projects end with sensors and charts that nobody uses. The difference between these two outcomes rarely depends on the algorithm. It depends on the order of actions at the start of the project. This article describes the sequence of actions that leads from measurement to a service decision.
Three maintenance strategies
Before starting, it is worth defining what predictive maintenance changes compared with the other strategies.
- Reactive maintenance means repair after a failure. It is simple, but the failure occurs at an unpredictable moment, often together with secondary damage.
- Preventive maintenance means inspections and replacements according to a calendar or an hour meter. It reduces failures, but some replacements concern components in good condition, and some damage still appears between inspections.
- Predictive maintenance means a repair decision based on the measured condition of the equipment. Intervention takes place when the data indicates deterioration, not when a date in the calendar comes up.
Predictive maintenance does not replace inspections. It complements them where the condition of the equipment can be measured and a failure is costly.
Step 1. Choose the machines you will start with
Do not start with the whole machine park. Choose a few pieces of equipment according to three criteria:
- Consequence of failure. A failure may mean stopping a line, losing a batch or a safety hazard. The greater the consequence, the more sense monitoring makes.
- A measurable failure mechanism. Bearing wear, imbalance, misalignment, wear of seals and filters, and overheating are visible in vibration, temperature, current or pressure.
- History. Equipment that has already failed has documented cases. This is valuable data for assessing whether monitoring would have detected the problem earlier.
Good candidates are usually pumps, fans, compressors, gearboxes, spindles and conveyor drives.
Step 2. Decide what to measure and where to get the data
A lot of data already exists. PLCs and SCADA systems record currents, pressures, temperatures and operating states. What is usually missing is vibration measurement, which shows mechanical damage earliest.
| Signal | What it shows | Typical source |
|---|---|---|
| Vibration (RMS, spectrum) | Bearings, imbalance, looseness, misalignment | Vibration sensor, e.g. with an IO-Link interface |
| Temperature | Friction, lubrication, overload | Sensor on the housing, PLC |
| Motor current | Load, seizing, changes in the process | Variable frequency drive, PLC |
| Pressure and flow | Pump wear, filter clogging | SCADA, process transmitters |
| Operating state | Operating context, that is start-up, running, stopped or product change | PLC, MES |
Operating context is as important as the measurement. The same vibration level may be normal at full load and worrying at idle. Without information about the operating state, the algorithm will raise false alarms at every product change.
Step 3. Separate anomaly detection from diagnosis
This is the most important principle of well-designed monitoring.
- Anomaly detection means that the equipment is behaving differently than usual. The model learns the machine’s normal operation and signals a deviation.
- Diagnosis means identifying the cause, for example a damaged bearing, a clogged filter or a loose mounting. The diagnosis is confirmed by a person through an inspection, a control measurement or a visual check.
A system that presents every anomaly as a certain diagnosis loses the team’s trust after a few mistakes. A system that says “a deviation of pump P-101 vibration from normal operation has been detected, history points to the bearing, inspection recommended” helps make a decision and clearly shows what is a fact and what is a hypothesis.
Step 4. Design the path from alarm to decision
An alarm that nobody responds to is worse than no alarm, because it teaches people to ignore signals. Before you launch monitoring, decide:
- Who receives the alarm and in what form, for example as a notification on the technician’s phone or an entry in the maintenance system.
- What the technician sees after opening the alarm, that is the signal trend, the equipment’s repair history and the inspection instruction.
- Who decides on the repair and based on what information, such as the availability of parts and people and the downtime window.
- Where the inspection result is recorded, so that subsequent alarms for this equipment have a fuller history.
Example sequence
Monitoring detects an increase in the vibration of pump P-101 over several days. The technician receives a notification, scans the QR code on the pump and sees the trend, the last bearing replacement and the inspection instruction. The inspection confirms bearing wear. The maintenance manager checks the availability of the bearing in stock and of a crew, and then schedules the replacement for the next downtime. The inspection result goes into the pump’s history.
Step 5. Decide how you will assess the effect
The effect of predictive maintenance does not appear in the first week. It is worth, however, defining metrics and a baseline from the start:
- the time from detecting a deviation to the decision to act,
- the share of planned repairs relative to emergency repairs for the monitored equipment,
- the number of alarms after which the inspection found no problem, as a measure of alarm quality,
- the completeness of the history, that is whether every intervention has its cause and the work performed recorded.
The last metric is often underestimated. Without a documented history, it is impossible to improve the models or draw conclusions from subsequent cases.
How to use historical data
Many plants have several years of data in their SCADA archives and a repair history in the maintenance system. This is valuable material, but only if the two data sets can be linked. It is worth checking:
- whether the entries in the repair history have a date, the equipment and a description of the cause, and not just “repaired”,
- whether the SCADA archive stores data at a sufficient frequency, or only averaged values,
- whether the equipment identifiers in both systems are the same.
If the historical data covers several cases of the same damage, you can check whether the signals before the failure changed in a repeatable way. Such an analysis makes it possible to assess the sense of monitoring for a given machine even before buying new sensors.
How to prepare the maintenance team
Condition monitoring changes the way the maintenance department works. Some calendar-based inspections are replaced by inspections driven by data, and the technician starts work by checking the trend rather than by dismantling the equipment. For this change to succeed:
- Involve technicians in choosing the machines. They know which equipment causes problems and which symptoms precede failures.
- Show where the alarm comes from. A technician who sees the trend and the comparison with normal operation trusts the signal more than an alarm message alone without an explanation.
- Collect inspection results. Every confirmation or exclusion of a problem improves the quality of subsequent alarms.
- Set a transition period. During the first weeks, monitoring runs in parallel with the existing inspections. The work schedule changes only after the results have been assessed.
The most common mistakes
- Buying sensors without a response plan. Data is collected, but nobody knows who is supposed to respond to it.
- Alarm thresholds from a catalog. General vibration standards are a starting point, but every machine has its own normal operating level. The model should account for the conditions of the specific installation.
- No operating context. Alarms during start-up, product change or load change quickly discourage the team.
- Too many pieces of equipment at the start. Several dozen monitored machines in the first month means dozens of alarms that the team will not manage to check. It is better to start with a few pieces of equipment and extend the scope after refining the way of responding.
- Promising to predict every failure. Not all damage gives early signals. Some failures, for example sudden mechanical or electrical damage, will still happen.
Summary
Predictive maintenance starts with a few well-chosen machines, not with buying sensors for the whole plant. For these machines you need to determine which signals show the failure mechanism, where to get the data and how to account for the operating context. Anomaly detection must be clearly separated from diagnosis, which is confirmed by a person.
The most important thing is the path from alarm to decision, that is deciding who receives the signal, what they see, who decides on the repair and where the result is recorded. Only when this path works does monitoring lead to planned repairs rather than just more charts.
How this works in WFS Platform
In WFS Platform, machine condition monitoring is handled by the Monitoring and diagnostics module. It collects data from sensors, PLCs and SCADA systems, calculates condition indicators and OEE, and detects anomalies based on models fitted to the operation of specific equipment. Anomaly detection is clearly separated from a confirmed diagnosis.
The technician receives the alarm in WFS Copilot on their phone. They see the trend, the equipment history and the procedure from the Documentation and processes module, and the Planning and resources module shows the availability of parts and people. The repair decision is approved by the maintenance manager.
Implementation starts with an audit and application test on one machine or line. The evaluation criteria, for example the time from alarm to decision, are agreed before the start. The result is a test report and a detailed cost estimate for the full implementation.